How an early construction budget is built, what each layer contains, and where feasibility-stage numbers usually go wrong. These guides sit between the cost calculator and a detailed estimate: use them to read a Class D range correctly before it goes into a pro forma, a board paper, or a lender conversation.
Planning guidance for owners, developers, and facility teams. Not a quotation or a basis for financing.
Run the Cost Calculator Back to ResourcesA Class D range is only useful if the reader knows what sits inside it and what does not. The guides below explain the layers in the order an owner meets them.
The three layers of a construction budget, typical Q4 2025 ratios for Ontario, the two kinds of contingency, and the five gaps that most often break an early budget.
What Class D means under AACE 18R-97, the ±20–30% accuracy band, how benchmark rates and multipliers combine, and why a conceptual range is not a quotation.
Hard-cost bands for warehouse, cold storage, office TI, restaurant, long-term care, industrial retrofit, daycare, medical office, self-storage, and manufacturing projects.
Owners who get a credible early number usually do it in this order. Each pass narrows the range and exposes the assumptions that need confirming.
Open the cost guide for your project type and read the GTA or secondary-Ontario band together with its inclusions and exclusions. Note what the band leaves out, such as process equipment, tenant fit-out, or land, so it can be added back later rather than forgotten.
Apply the soft-cost groups as a checklist rather than a flat percentage, take development charges from the current municipal by-law, and carry design and construction contingency as separate line items with release conditions.
The calculator applies the same layers to your inputs and returns a Class D range with allowances and compliance flags. If the project is large, permit-sensitive, or in an unfamiliar municipality, move to a detailed estimate inquiry and, where the scope is technical, engineering review.
Class D range with soft costs, contingency, development charges, and compliance triggers.
How fixed-price, cost-plus, and construction management change who carries contingency and cost risk.
Utility capacity, structural reuse, change of occupancy, PSHSR under Reg. 851, and site servicing are budget items that only an engineering review can size. ProWise Engineering, our sister practice, provides that review before the number is treated as actionable.
Visit ProWise EngineeringRun the calculator for a Class D range, then request a detailed estimate inquiry if the project needs a reviewed number.
Run the Cost Calculator Request a Detailed EstimateClass D conceptual estimate information only, per AACE International Recommended Practice 18R-97. Not a quotation. Not a basis for financing or contract value. Development charge and permit fee figures must be taken from the current municipal by-law and fee schedule. Material decisions require qualified engineering and quantity-surveying review.