Most early budgets that fail in Ontario do not fail on the building. They fail on everything around it: fees, approvals, development charges, and the allowance for what is not yet designed. This page explains the three layers of a commercial construction budget and the ratios to expect at feasibility stage.
Planning guidance for owners, developers, and facility teams. Not a quotation or a basis for financing.
Run the Cost Calculator Read How Estimates WorkEarly budgets usually get the first layer roughly right and the other two wrong. Keeping them separate is the single most useful habit at feasibility stage.
What the contractor builds: structure, envelope, interiors, mechanical and electrical systems, and site work. The largest layer, and the one most people picture when they ask "what does it cost per square foot".
Everything required to get the building designed, approved, financed and handed over, but not physically built into it: consultant fees, permits, development charges, legal, owner-side and carrying costs.
The explicit allowance for cost that is expected to exist but cannot yet be itemized. Two kinds at feasibility stage: design contingency and construction contingency, carried separately.
Each step below adds to the one before it. Together they explain why a total project cost in Ontario is commonly 1.35 to 1.55 times the hard-cost figure before land and financing.
When a cost guide quotes a hard-cost range, for example C$115–175 per sq ft for a GTA warehouse shell, it normally includes the following.
Foundations, slab-on-grade, steel or precast frame, roof deck.
Wall systems, roofing, glazing, doors, loading docks.
Partitions, finishes, washrooms, and base-building office area where stated.
HVAC, plumbing, fire protection, lighting, power distribution, and the base electrical service.
Grading, paving, storm and sanitary servicing on site, landscaping, and site lighting.
Site supervision, temporary works, insurance, bonding, overhead and profit.
Soft costs sit between a site and an occupied building. On Ontario commercial and industrial projects at Q4 2025 benchmarks, a typical soft-cost overlay is 18–28% of hard cost, before land and financing. The spread comes from four groups.
Architecture, structural, mechanical, electrical, civil, and specialty consultants (fire protection, geotechnical, environmental, traffic, landscape). Full design fees commonly run 5.5–12% of hard cost; a straightforward industrial building sits toward the low end, while healthcare or food-grade facilities climb because the consultant team is larger and review cycles are longer.
Building permit fees, site plan application fees, development charges, parkland dedication or cash-in-lieu, education development charges, and utility connection charges. Development charges are set by municipal by-law under the Development Charges Act, 1997, levied by the local municipality and, in two-tier regions such as Peel, York, Halton and Durham, by the regional municipality as well, and calculated per square foot of gross floor area for non-residential buildings.
Legal, surveying, project management or owner's representative (commonly 1–2.5% of hard cost), commissioning, moving, furniture and equipment, builder's risk insurance where the owner carries it (1–1.5%, higher on recent Q4 2025 broker quotes), and marketing where relevant.
Interest during construction, property tax on the land during the build, and temporary facilities. Usually shown separately from the soft-cost percentage because they depend on the owner's financing structure, not on the building.
Contingency is not padding. It is the explicit allowance for cost that the estimate class cannot yet resolve. At feasibility stage there are two kinds, and they should be carried separately.
About 10–15% of hard cost at Class D
Covers scope that will be added as drawings develop: a mezzanine stair that was not on the concept sketch, the electrical service upgrade discovered during utility coordination, the storm-water control the municipality asks for at site plan. It shrinks as the design matures and should be close to zero at tender.
About 5–10% for new builds
Covers unknowns during the build: unforeseen soil conditions, latent conditions in existing buildings, weather, and owner-directed changes. Retrofits of occupied or older buildings often warrant more because the existing conditions are less certain.
A simplified Class D build-up for an Ontario commercial project, Q4 2025 basis.
| Layer | Typical ratio | Note |
|---|---|---|
| Hard cost | 100% (base) | From the relevant cost guide range, adjusted for site and specification |
| Soft costs (design, municipal, owner) | +18–28% | Development charges from the municipal rate schedule, not a percentage |
| Design contingency | +10–15% of hard cost | Releases as design matures |
| Construction contingency | +5–10% of hard cost | Releases as risk closes out |
| Carrying costs, land, HST | Shown separately | Depend on financing and ownership structure |
Across the projects we review, the same five gaps appear.
The single largest soft-cost error on GTA industrial projects.
Watermain, sanitary or road upgrades conditioned in site plan approval are owner costs.
With no split between design and construction contingency and no release plan.
Because the cost guide range excluded them, and nobody added them back.
From the number given to the lender or the board.
None of these is a construction problem. All of them are budget-structure problems that an engineering-informed pre-construction review catches early. Utility capacity, structural reuse, change of occupancy and site servicing are budget items that only an engineering review can size.
Hard costs are the physical construction of the building and site, including structure, envelope, interiors, mechanical and electrical systems, site work, and the contractor's general conditions and fee. Soft costs are the fees and charges needed to design, approve, finance and hand over the building, such as consultant fees, permits, development charges, legal and owner-side costs.
At Q4 2025 benchmarks, a typical soft-cost overlay on Ontario commercial and industrial projects is 18–28% of hard cost before land and financing. The range depends mainly on the consultant team required and on municipal development charges, which vary materially between municipalities and should be taken from the current rate schedule.
At feasibility (Class D) stage, carry a design contingency of about 10–15% of hard cost for scope that will emerge as drawings develop, plus a construction contingency of about 5–10% for unknowns during the build. Carry them as separate line items and tie each to a release condition rather than hiding them inside unit rates.
The ratios on this page are the same planning values the ProWise cost calculator applies, assembled from published Canadian cost references, Ontario municipal and regulatory inputs, and our own recent project pricing, indexed to the Q4 2025 basis quarter. They are planning benchmarks, not a quotation.
Altus Group Canadian Cost Guide (Ontario and GTA unit-rate bands by building type); RSMeans / Gordian construction cost data with Toronto and regional Ontario city cost indexes; Infrastructure Ontario project database (public-sector project cost records across building types); Statistics Canada Building Construction Price Index (Toronto CMA, non-residential) for indexing published figures to the basis quarter.
Development charge by-laws and rate schedules of GTA lower- and upper-tier municipalities (including Toronto, Peel, York, Halton, and Durham) and of secondary Ontario markets; municipal building permit fee schedules; Ontario Building Code classification thresholds that change design-fee and compliance scope.
Recent ProWise Construction tender pricing and ProWise Engineering design and permit work across industrial, commercial, restaurant, and institutional projects in the GTA. We use this to sanity-check published fee and contingency bands against actual project outcomes, not to replace them.
Run the calculator for a Class D range with soft costs and contingency carried explicitly. If the project is large, permit-sensitive, or in an unfamiliar municipality, request a detailed estimate inquiry.
Run the Cost Calculator Request a Detailed EstimateClass D conceptual estimate information only, per AACE International Recommended Practice 18R-97. Ratios are typical Q4 2025 planning values for Ontario commercial and industrial projects and are not a quotation, a financing basis or a contract value. Development charge and permit fee figures must be taken from the current municipal by-law and fee schedule. Material decisions require qualified engineering and quantity-surveying review.